PDM includes four types of dependencies or precedence relation ships:(73)The completion of

题目

PDM includes four types of dependencies or precedence relation ships:(73)The completion of the successor activity depends upon the initiation of the predecessor activity.

A.Finish-to-Start

B.Finish-to-Finish

C.Start-to-Start

D.Start-to-Finish

参考答案和解析
正确答案:D
解析:前导图法包括四种活动依赖或前导关系:开始-结束。后续活动的结束依赖于前导活动的开始。