120The Work Breakdown Structure (WBS) is the basis for communicating: A.Project scope, cos

题目

120 The Work Breakdown Structure (WBS) is the basis for communicating:

A. Project scope, cost control, schedule, quality

B. Project objectives, dependencies, plan, cost control

C. Project scope, schedule, staffing, cost control

D. Project scope, quality, schedule, dependencies

E. Project budget, schedule, risk factors, work assignments

参考答案和解析
正确答案:A