6 A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks most likely, and 12 weeks pessimistically. The expected time which would appear on the chart would be:

A. 4 weeks

B. 5 weeks

C. 6 weeks

D. 7 weeks

E. None of the above

参考答案和解析
正确答案:B