题目

105 Which of the following actions is an example of risk response:

A. adjust project parameters (scope, time, quality ...)

B. reduce the probability of potential project risk events

C. reduce the consequences of potential project risk events

D. wait until a problem actually happens, then deal with it in the most effective and efficient manner.

E. A, B and C only