96A negative cost variance and positive schedule variance means: A.The project is under bu

题目

96 A negative cost variance and positive schedule variance means:

A. The project is under budget and ahead of schedule

B. The project is over budget and behind schedule

C. The project is over budget and ahead of schedule

D. The project will be overrun but ahead of schedule at completion