●Using the data shown in the Special window, Activities P, Q, and T are critical path acti
题目
● Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?
A P
B Q
C R
D S
E T
参考答案和解析
正确答案:A