The( )provides the project manager with the authority to apply organizational resources t

题目

The( )provides the project manager with the authority to apply organizational resources to project activities。

A.project management plan

B.project charter

C.project human resource plan

D.project stakeholders

参考答案和解析
正确答案:B
项目章程(project charter)为项目经理使用组织资源进行项目活动提供了授权。