● The Estimate Activity Resource process is closely coordinated with the (73)process. (73)

题目

● The Estimate Activity Resource process is closely coordinated with the (73)process.

(73)

A. Estimate Costs

B. Sequence Activities

C. Plan Communications

D. Conduct Procurements